Economics

Operating costs: the purchase price is the smaller part.

Over a service life of eight to ten years, consumable, wear, and energy costs clearly exceed the investment at typical utilisation. Comparing quotes on purchase price alone compares the smaller line item.

Investment AnalysisReading time 8 minUpdated 2026-08-27

Cost structure of an abrasive cutting station

The following model describes a typical single-head cutting station at 4,000 bar and roughly 37 kW connected load, running two shifts. The figures are worked examples, not market prices; their purpose is to make the relative order of magnitude visible.

Consumable and wear cost per operating hour, worked example
ItemBasisCostShare
Abrasive0.35 kg/min = 21 kg/h at €0.40/kg€8.40/h33%
Energy37 kW at €0.26/kWh€9.62/h38%
Disposal of abrasive and removed material21 kg/h at €0.15/kg€3.15/h12%
Wear partswater orifice, focusing tube, seals, valves€3.50/h14%
Water and treatmentroughly 0.23 m³/h including pretreatment€0.90/h4%
Total consumables and wearexcludes machine-hour rate and labour€25.57/h100%

Worked example for order of magnitude. Energy and disposal prices vary considerably by region and over time and should be checked for the specific case.

Operating Cost per Hour Consumable and wear cost of an abrasive cutting station. Excludes machine-hour rate, labour, and floor space.
Abrasive8.40€/h
Energy9.62€/h
Abrasive disposal3.15€/h
Wear parts3.50€/h
Water and treatment0.90€/h
Total25.57€/h
Abrasive share including disposal45%

Annual cost approximately €76,700.

Fixed assumptions in the model: disposal €0.15/kg abrasive, wear parts €3.50/h (water orifice, focusing tube, seals, valves), water including treatment €0.90/h at roughly 0.23 m³/h. A machine-hour rate for depreciation, floor space, labour, and maintenance work is not included.

The actual cost drivers

A notable feature of the model is that abrasive and disposal together make up nearly half of consumable cost, while wear parts — the item negotiated most intensively during procurement — account for only around a seventh. The most effective levers therefore lie elsewhere.

Effectiveness of typical optimisation approaches
ApproachCost ImpactImplementation EffortRisk
Assign quality grade per contour
Optimise abrasive mass flow
Improve part nesting
Introduce abrasive recycling
Negotiate a discount on wear parts
Run at higher operating pressure
Reduce idle time under pressure hold

Five points denotes the strongest effect. For risk, a high value means a greater chance of unwanted side effects, such as increased wear.

The overlooked line item

None of the figures above include unplanned downtime. A single unforeseen four-hour outage on a two-shift operation can cost several times what a full week of wear parts amounts to, depending on the machine-hour rate and delivery schedule. Spare-parts availability and the service partner's response time therefore belong in the economic analysis, not in an appendix.

Putting quotes on a comparable basis

  • Same operating pointReference every quote to the same pressure, flow rate, and nozzle configuration
  • Consumption per reference partDefine an actual part and ask for abrasive consumption and time per part
  • Connected load and efficiencyRequest electrical power at the operating point, not the nominal motor rating
  • Priced wear-parts listAsk for service life and list prices of consumable parts over three years
  • Service conceptQuantify response time, spare-parts availability, remote access, and maintenance contract
  • Complete peripheralsInclude water treatment, abrasive feed, extraction, disposal, and foundation
  • Residual-value assumptionFix service life and residual value consistently, or full-cost comparisons aren't comparable

Frequently asked questions about economics

When does an in-house system pay off compared with job-shop cutting?

The threshold is less about part count than utilisation. As a rough rule: below a reliable baseline utilisation of about one shift, job-shop cutting usually remains cheaper, because fixed costs and building up expertise cannot be spread. Non-monetary factors such as turnaround time, confidentiality, and prototyping capability can shift the calculation in specific cases.

How strongly does operating pressure affect cost?

In two directions at once. Higher pressure increases traverse speed and so reduces time per part, but simultaneously raises energy demand and wear on pressure-carrying components disproportionately. The economical operating point is therefore rarely at the top of the performance range.

Is abrasive recycling worthwhile?

Yes, at high, steady utilisation and high local disposal costs. The calculation weighs saved new material plus avoided disposal against the investment, energy, maintenance, and operating effort of the recycling unit. On single-shift operation, it usually does not pay off.